Ridgeacres & Yosemite Road Projects Announced Starting in July

GOLF MANOR (5/7/2025) – If you haven’t already heard the good news, contracts have been approved by Council, signed by the Administration and the construction project to renovate Ridgeacres Avenue & Yosemite Drive is moving ahead full speed.

The project is funded by the Village of Golf Manor with grant funding from the Southwest Ohio Regional Transit Authority (SORTA) and the State of Ohio Public Works Commission (OPWC).

The scope of the project will include installing new water lines and fire hydrants on Yosemite and replacement of curbs along the entire length of both roads in the Golf Manor jurisdiction. The entire street will be resurfaced with new asphalt. Finally, speed control devices (humps) will be installed at the conclusion of the project. Curbs will be replaced with box curbs, as we are installing throughout the Village which are better for controlling storm water.

We anticipate that construction will begin sometime around the end of July/mid-August with the concrete and catch basins. Installation of new water lines then milling and leveling of the asphalt will begin in early September. Removal of curbs and driveway aprons as well as sections of sidewalk to be replaced will also begin about that time. The completion of the project is anticipated to occur mid-October.

We apologize in advance for the frustration that goes along with a major residential street project like this. You will likely experience some delays along with limited access to your driveway. The contractor, Adleta, Inc., who specializes in these types of projects, will directly notify you of any disruptions in traffic or parking as the various phases of the project are carried out. Every effort will be made to ensure you have access to your driveway as the project proceeds. Adleta has partnered with Golf Manor on several projects like this before and is very responsive to resident needs.

You will be able to stay up-to-date on progress of the project by going to the Village website at  https://www.golfmanoroh.gov/road-construction-projects/.

Always use our website to find updates on this and other projects throughout the Village, a great resource for events, ordinances and other information vital to Village operations.

Anticipated Timeline

Project Phase Start Date Projected End Date
Concrete & Catch Basin Work 8/11/2025 9/26/2025
Water Main Work on Yosemite 9/11/2025 10/1/2025
Asphalt Application & Adjustments 10/6/2025 10/10/2025
Reclamite/Line Striping/Signage 10/13/2025 10/18/2025

 

Leave a Reply


Join Us for Planting Day – Tuesday, May 20, 2025 @ 9 AM

GOLF MANOR (4/25/2025) – Join the Golf Manor Administration and Service employees in giving the Village a natural color boost ...

Ridgeacres & Yosemite Road Projects Announced Starting in July

GOLF MANOR (5/7/2025) – If you haven’t already heard the good news, contracts have been approved by Council, signed by ...

Report from Mayor Stefan Densmore – 4/28/2025

GOLF MANOR (4/28/2025) – Report from Mayor Stefan Densmore I swore in Nick Hochscheid as a part time officer in ...

Community Clean-Up Day on Saturday, May 31

GOLF MANOR (4/25/2025) – Join us for a day of giving back and getting our hands a little dirty — ...