Vera/Short Elbrook/West Service Drive/Short Fair Oaks

This project is ongoing. Projected completion scheduled by the end of October 2021.

Update: (8/31/2021) – New water main pipe continues to be installed on short Elbrook, Vera and short Fair Oaks. The pipe is being prepped and sanitized for use as it is being installed. Residents will be notified by GCWW and the contractor when the new water main is activated. When the water main project is completed, crews will start removing and replacing the curb.

Update: (8/5/2021) – Removal of pavement continues on Vera moving east toward Fair Oaks. This phase one of the project is in preparation for the Greater Cincinnati Water Works to replace the water main.

Update: (7/27/2021) – We have been advised by the contractor that removal of pavement for the new water main will begin on north Elbrook on Wednesday, July 28 and continue up Vera until the installation of the main is complete. Fair Oaks from Vera to Losantiville will also be added to this project as a part of the water main replacement. As a result, new curbs and pavement will be installed on this section of road.

Update: (6/11/2021) – The contractor has updated us today confirming that staging for construction including lay out of the water main and storm sewers will take place the week of June 21st with saw cutting starting the week of June 28th. Water main installation will start the week of July 4th.

Update: (5/17/2021) – The Village has been advised by the contractor for the Vera/Elbrook Road project that the start of construction has been delayed until the third week in June. We were anticipating the start to be the week of May 17.  This was a last-minute development that the contractor failed to communicate to the Village. The contractor advised the delay is necessary due to a delay in another project that the crew coming to Golf Manor is experiencing in another project in Hamilton.

The up-side to this is that this will not drag out our project but will in fact compress the time they will be working in the Village. Our project will still be complete by mid-October.

Watch this space for further information and updates.

ORIGINAL ANNOUNCEMENT

Golf Manor (5/10/2021) – If you haven’t already heard the good news, Council has approved the project, contracts have been signed, and the construction project to renovate the entire length of Vera Avenue, the western service drive, and Elbrook from Losantiville to the Amberley corporation line (Short Elbrook) is moving ahead full speed.

The scope of the project will include installation of new curbs on Vera and Short Elbrook. Both streets along with the western service drive will be  resurfaced with new pavement. We will also be installing permanent speed control devices (speed humps) as part of the project on Vera and Short Elbrook. In addition, the Greater Cincinnati Water Works will be replacing the water main on both streets as the first phase of the project begins in May 2021.

We will notify residents of specifics of the project as soon as details are worked out in initial construction meetings.

We understand the frustration that goes along with major residential street projects when they occur and apologize in advance for any delays, parking issues, or other inconvenience residents may experience during the project.

The Village of Golf Manor will not directly perform any of the work. Adleta Construction has been awarded the project and will develop the construction schedule and do all of the construction work and traffic/parking management. They will also directly notify you of any disruptions in traffic or changes in parking needed as the various phases of the project are carried out. We will need resident cooperation during these important changes in order to allow this project to move along as quickly as possible.

You will be able to stay up-to-date on progress of the project by visiting this page. Information will be will be posted as we get information from the contractor.

Contact Information

Your first call regarding questions about the project need to be directed to the contractor:

Contact Name Organization Phone Email
Adleta Construction
Bob Sturgill – Project Liaison JMA Consultants – Road Engineer 513-504-8080 roadconstruction@golfmanoroh.gov
Andy Lanser Asst. Administrator/Service Dept. 513-531-7491 x305 a.lanser@golfmanoroh.gov
Ron Hirth Village Administrator 513-531-7491 x300 info@golfmanoroh.gov

 


Temporary Signs Permitted Following Ordinance Requirements

GOLF MANOR (10/7/2021) - As we get closer to the November 2nd general election it's great to see folks participate ...
Read More »

GM Candidates & Issue On Ballot for Tuesday, November 2 General Election

GOLF MANOR (9/22/2021) – This coming General Election Day, Tuesday, November 2, 2021, will see one tax levy renewal issue ...
Read More »

Fall 2021 Edition of “The Villager” Newsletter Now Online

GOLF MANOR (8/31/2021) – The Fall 2021 edition of The Villager newsletter is now available here. Topics in this issue: ...
Read More »

Village Offices Closed Monday, September 6, 2021 for Labor Day Holiday

GOLF MANOR (8/27/2021) – The Village of Golf Manor Administration offices will be closed on Monday, September 7, 2021 in ...
Read More »