2017 Losantiville Road Project

(9/6/2017): Work on Losantiville starts today. Prus will begin saw-cutting curbs near Wiehe and progress going east  on the right side of the roadway headed toward Montgomery Road.

(8/10/2017): Mayor Ron Hirth, Village Engineer Tim King, and  Paul Long, Vice President of Prus Construction, held a pre-construction meeting on August 10, 2017  to review contracts and the scope of the project and lock in our pricing. Curb repair will start in October 2017 with the project being complete by December. More updates as we have them…

Related News

Leave a Reply


Temporary Signs Permitted Following Ordinance Requirements

GOLF MANOR (10/7/2021) - As we get closer to the November 2nd general election it's great to see folks participate ...
Read More »

GM Candidates & Issue On Ballot for Tuesday, November 2 General Election

GOLF MANOR (9/22/2021) – This coming General Election Day, Tuesday, November 2, 2021, will see one tax levy renewal issue ...
Read More »

Fall 2021 Edition of “The Villager” Newsletter Now Online

GOLF MANOR (8/31/2021) – The Fall 2021 edition of The Villager newsletter is now available here. Topics in this issue: ...
Read More »

Village Offices Closed Monday, September 6, 2021 for Labor Day Holiday

GOLF MANOR (8/27/2021) – The Village of Golf Manor Administration offices will be closed on Monday, September 7, 2021 in ...
Read More »