2017 Losantiville Road Project

(9/6/2017): Work on Losantiville starts today. Prus will begin saw-cutting curbs near Wiehe and progress going east  on the right side of the roadway headed toward Montgomery Road.

(8/10/2017): Mayor Ron Hirth, Village Engineer Tim King, and  Paul Long, Vice President of Prus Construction, held a pre-construction meeting on August 10, 2017  to review contracts and the scope of the project and lock in our pricing. Curb repair will start in October 2017 with the project being complete by December. More updates as we have them…

Related News

Leave a Reply


Village Council Approves Free Community Library Installations on Residential A Zoned Properties

GOLF MANOR, OH (5/3/2021) - Free Community Libraries are coming to the Village of Golf Manor! After careful study and ...
Read More »

New Guidance Issued for COVID – 19 Precautions at Municipal Building

GOLF MANOR, OH (4/28/2021) - Golf Manor Village Administrator Ron Hirth has announced that new guidelines issued by the Center ...
Read More »

Village Council Reviews Fire/EMS Services

GOLF MANOR, OH (4/26/2021)– Village of Golf Manor Mayor Stefan Densmore has announced that the Village Council is reviewing fire ...
Read More »

LMFR Board Virtual Meeting Wednesday, April 21, 2021 @ 6PM

GOLF MANOR (4/21/2021) – The Board of Trustees of the Little Miami Fire & Rescue District will meet virtually for ...
Read More »