Golf Manor (8/11/2023) – Remaining full depth repairs (which we documented contemporaneous with the milling) are scheduled to be performed next Thursday (8/17), along with the manhole and valve casting adjustments.
Golf Manor (4/4/2023) – Construction begins on Wiehe road on Wednesday, April 5. No parking has been posted starting that day.
The Village of Golf Manor has contracted with Adleta Construction Company, a professional road construction contractor who specializes in road improvement projects. The contractor will directly notify residents and businesses of any disruptions in traffic or parking as the various phases of the project are carried out. Every effort will be made to ensure you have access to your driveway as the project proceeds.
Construction Schedule*
Activity | Anticipated Dates |
Tree removal | 2/27/2023 to 3/3/2023 |
Pavement Planing | 3/27/2023 to 3/31/2023 |
Leveling Course | 4/2/2023 to 4/7/2023 |
Catch basin repairs, curb, sidewalks & driveway aprons | 4/10/2023 to 5/26/2023 |
Full depth repairs | 5/29/2023 to 6/9/2023 |
Surface course, rejuvenator & pavement markings7 | 7/12/2023 to 7/23/2023 |
Final restoration & punch list | 7/26/2023 to 7/30/2023 |
*Although every effort will be made to follow the proposed schedule, weather conditions and other factors unforeseen may cause delays or require adjustments in timing.
Contacts
Contractor – Adleta Construction Company | Tyler Reusch – Supervisor | treusch@adletaconstruction.com | 513-554-1469 |
Contractor – Adleta Construction Company | Mark Swanner – Foreman | ||
Golf Manor Public Works Manager | Jim Puthoff | j.puthoff@golfmanoroh.gov | 513-800-6158 |